Mass Cost Updates

Hello,

In the previous version of Vantage, when we entered a cost for a part in the Cost Adjustment screen, it applied the cost to all three of our plants. With the new version, we have to enter the costs seperately for each plant. That means that for each part we enter, we need to switch through three plants, go into Cost Adjustment, and input our cost. This is very time consuming and we have about 3000 parts that need costs added to them.

Does anyone know of a way to do a mass import of costs, without having to enter them part-by-part, plant-by-plant in the Cost Adjustment screen? Even if we have to write directly to database tables, we are open to suggestions. Any help would be much appreciated. Thank you.