Looking to see if anyone knows a way to mass change all jobs to another resource NOT resource group in Vantage 8+? Maybe missing an out of the box feature somewhere, but am open to suggestions to customize.
Right now having a bit of trouble using the adapters to update the JobOpDtl and then also change the scheduled resource using code. This would be an ongoing thing to batch change jobs between resources.

Short answer? No… there is no way to do that except viea customization / bpm or some external program.