Hi,
When we run MRP, it is pushing out jobs way into the future even though we have the parts/ materials to work the jobs sooner. It seems that MRP is not considering the material in stock and is just looking at the lead time of the materials feeding the top level.
However, when we go to reschedule the jobs manually, everything reverts how it should to the appropriate time timeline. How do we get MRP to consider inventory when scheduling jobs rather than pushing everything to its lead time?
Thank you,