MRP not working correctly in 5.0

We're on 5.10.115 now and use MRP. We made the jump from 4.00.904 directly
to 5.10 over Thanksgiving , so we didn't play any in 5.0. We recently ran
into problems with MRP, turned out it was because we didn't RTFM (Read The
Friggin Manual)on 5.0 re MRP changes. As of our MRP run last night, it
seems to be working correctly. All the jobs we locked down were ignored by
MRP, with any demand changes generating new unfirm jobs. Tech support was
helpful (and patient!) with me about it, too. Anything else I can do, let
me know.
Alan
-----Original Message-----
Message: 1
Date: Wed, 30 Jan 2002 13:39:21 -0600
From: "Heisey, Lois" <lheisey@...>
Subject: RE: MRP not working correctly in 5.0

Troy... we are submitting the documentation to Epicor now as we speak.

-----Original Message-----
From: Troy Funte [mailto:tfunte@...]
Sent: Wednesday, January 30, 2002 1:23 PM
To: vantage@yahoogroups.com
Subject: Re: [Vantage] MRP not working correctly in 5.0


Hi,
I'll forward this to our Materials manager to look at this. We are
having similar issues and maybe we can nail it down so it can be reproduced
and submitted to Epicor.

Troy Funte
Liberty Electronics

----- Original Message -----
From: lheisey3
To: vantage@yahoogroups.com
Sent: Wednesday, January 30, 2002 9:32 AM
Subject: [Vantage] MRP not working correctly in 5.0


MRP processing is using MRP suggestions to suggest changes to jobs
that have both the quantity and the date "locked" on the job. This
is resulting in bad job data generated by MRP where you don't want
those dates and quantity suggestions taken into consideration in the
processing. This happens whether you run net change or full MRP
regeneration (help desk did confirm that bug in the system will not
trigger a change when the only change to a record is the locked
toggle boxes being turned on). Has anyone else experienced this
problem in their MRP processing? We have taken out all variables
(minimum stock quantities, minimum mfg. quantities, etc.) and still
get the same effect. Is anyone out there using MRP and if so how?
Does MRP work correctly in 5.1? Any help would really be
appreciated!

Thanx,
Alan
MRP processing is using MRP suggestions to suggest changes to jobs
that have both the quantity and the date "locked" on the job. This
is resulting in bad job data generated by MRP where you don't want
those dates and quantity suggestions taken into consideration in the
processing. This happens whether you run net change or full MRP
regeneration (help desk did confirm that bug in the system will not
trigger a change when the only change to a record is the locked
toggle boxes being turned on). Has anyone else experienced this
problem in their MRP processing? We have taken out all variables
(minimum stock quantities, minimum mfg. quantities, etc.) and still
get the same effect. Is anyone out there using MRP and if so how?
Does MRP work correctly in 5.1? Any help would really be
appreciated!
Hi,
I'll forward this to our Materials manager to look at this. We are having similar issues and maybe we can nail it down so it can be reproduced and submitted to Epicor.

Troy Funte
Liberty Electronics

----- Original Message -----
From: lheisey3
To: vantage@yahoogroups.com
Sent: Wednesday, January 30, 2002 9:32 AM
Subject: [Vantage] MRP not working correctly in 5.0


MRP processing is using MRP suggestions to suggest changes to jobs
that have both the quantity and the date "locked" on the job. This
is resulting in bad job data generated by MRP where you don't want
those dates and quantity suggestions taken into consideration in the
processing. This happens whether you run net change or full MRP
regeneration (help desk did confirm that bug in the system will not
trigger a change when the only change to a record is the locked
toggle boxes being turned on). Has anyone else experienced this
problem in their MRP processing? We have taken out all variables
(minimum stock quantities, minimum mfg. quantities, etc.) and still
get the same effect. Is anyone out there using MRP and if so how?
Does MRP work correctly in 5.1? Any help would really be
appreciated!



Yahoo! Groups Sponsor
ADVERTISEMENT




Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must have already linked your email address to a yahoo id to enable access. )
(1) To access the Files Section of our Yahoo!Group for Report Builder and Crystal Reports and other 'goodies', please goto: http://groups.yahoo.com/group/vantage/files/.
(2) To search through old msg's goto: http://groups.yahoo.com/group/vantage/messages
(3) To view links to Vendors that provide Vantage services goto: http://groups.yahoo.com/group/vantage/links

Your use of Yahoo! Groups is subject to the Yahoo! Terms of Service.



[Non-text portions of this message have been removed]
Troy... we are submitting the documentation to Epicor now as we speak.

-----Original Message-----
From: Troy Funte [mailto:tfunte@...]
Sent: Wednesday, January 30, 2002 1:23 PM
To: vantage@yahoogroups.com
Subject: Re: [Vantage] MRP not working correctly in 5.0


Hi,
I'll forward this to our Materials manager to look at this. We are
having similar issues and maybe we can nail it down so it can be reproduced
and submitted to Epicor.

Troy Funte
Liberty Electronics

----- Original Message -----
From: lheisey3
To: vantage@yahoogroups.com
Sent: Wednesday, January 30, 2002 9:32 AM
Subject: [Vantage] MRP not working correctly in 5.0


MRP processing is using MRP suggestions to suggest changes to jobs
that have both the quantity and the date "locked" on the job. This
is resulting in bad job data generated by MRP where you don't want
those dates and quantity suggestions taken into consideration in the
processing. This happens whether you run net change or full MRP
regeneration (help desk did confirm that bug in the system will not
trigger a change when the only change to a record is the locked
toggle boxes being turned on). Has anyone else experienced this
problem in their MRP processing? We have taken out all variables
(minimum stock quantities, minimum mfg. quantities, etc.) and still
get the same effect. Is anyone out there using MRP and if so how?
Does MRP work correctly in 5.1? Any help would really be
appreciated!



Yahoo! Groups Sponsor
ADVERTISEMENT




Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must
have already linked your email address to a yahoo id to enable access. )
(1) To access the Files Section of our Yahoo!Group for Report Builder and
Crystal Reports and other 'goodies', please goto:
http://groups.yahoo.com/group/vantage/files/.
(2) To search through old msg's goto:
http://groups.yahoo.com/group/vantage/messages
(3) To view links to Vendors that provide Vantage services goto:
http://groups.yahoo.com/group/vantage/links

Your use of Yahoo! Groups is subject to the Yahoo! Terms of Service.



[Non-text portions of this message have been removed]



Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must have
already linked your email address to a yahoo id to enable access. )
(1) To access the Files Section of our Yahoo!Group for Report Builder and
Crystal Reports and other 'goodies', please goto:
http://groups.yahoo.com/group/vantage/files/.
(2) To search through old msg's goto:
http://groups.yahoo.com/group/vantage/messages
(3) To view links to Vendors that provide Vantage services goto:
http://groups.yahoo.com/group/vantage/links

Your use of Yahoo! Groups is subject to http://docs.yahoo.com/info/terms/