PO suggestion for Subcontracted Operation didn't show up

Hi Michael

PO Suggestions only creates subcontract suggestions and purchase direct
suggestions for firm jobs (Not Unfirm)

I am guessing it is to do with linking the records to firm job numbers

Hope this helps

Gary

_____

From: ami_miker [mailto:michael.randolph@...]
Sent: 13 January 2005 16:21
To: vantage@yahoogroups.com
Subject: [Vantage] PO suggestion for Subcontracted Operation didn't show
up.



After I got down from my Subcontracting soapbox, I ran into a new
quirk. Is there any reason why MRP would generate material
suggestions for a job, but not subcontracted PO suggestions? I have
been assured by the production manager that the operation was there
before MRP ran. (He did admit that the material was added a day
before this particular operation.) I think this is just an internal
timing mistake, but I was wondering if there was anything that would
cause this.

Thanks!

Michael Randolph
Purchasing Manager
American Magnetics, Inc.






Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must
have already linked your email address to a yahoo id to enable access. )
(1) To access the Files Section of our Yahoo!Group for Report Builder
and Crystal Reports and other 'goodies', please goto:
http://groups.yahoo.com/group/vantage/files/.
(2) To search through old msg's goto:
http://groups.yahoo.com/group/vantage/messages
(3) To view links to Vendors that provide Vantage services goto:
http://groups.yahoo.com/group/vantage/links



_____

Yahoo! Groups Links


* To visit your group on the web, go to:
http://groups.yahoo.com/group/vantage/

* To unsubscribe from this group, send an email to:
vantage-unsubscribe@yahoogroups.com
<mailto:vantage-unsubscribe@yahoogroups.com?subject=Unsubscribe>

* Your use of Yahoo! Groups is subject to the Yahoo! Terms of
Service <http://docs.yahoo.com/info/terms/> .




[Non-text portions of this message have been removed]
After I got down from my Subcontracting soapbox, I ran into a new
quirk. Is there any reason why MRP would generate material
suggestions for a job, but not subcontracted PO suggestions? I have
been assured by the production manager that the operation was there
before MRP ran. (He did admit that the material was added a day
before this particular operation.) I think this is just an internal
timing mistake, but I was wondering if there was anything that would
cause this.

Thanks!

Michael Randolph
Purchasing Manager
American Magnetics, Inc.
Michael:
Did you run generate PO suggestions from purchasing? MRP generates material
suggestions, but you need to run PO suggestions in order to
get the subcontract service suggestions.

Julie Lehmann
MERCURY MINNESOTA INC.

----- Original Message -----
From: "ami_miker" <michael.randolph@...>
To: <vantage@yahoogroups.com>
Sent: Thursday, January 13, 2005 10:21 AM
Subject: [Vantage] PO suggestion for Subcontracted Operation didn't show up.


>
>
> After I got down from my Subcontracting soapbox, I ran into a new
> quirk. Is there any reason why MRP would generate material
> suggestions for a job, but not subcontracted PO suggestions? I have
> been assured by the production manager that the operation was there
> before MRP ran. (He did admit that the material was added a day
> before this particular operation.) I think this is just an internal
> timing mistake, but I was wondering if there was anything that would
> cause this.
>
> Thanks!
>
> Michael Randolph
> Purchasing Manager
> American Magnetics, Inc.
>
>
>
>
>
>
> Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must
have already linked your email address to a yahoo id to enable access. )
> (1) To access the Files Section of our Yahoo!Group for Report Builder and
Crystal Reports and other 'goodies', please goto:
http://groups.yahoo.com/group/vantage/files/.
> (2) To search through old msg's goto:
http://groups.yahoo.com/group/vantage/messages
> (3) To view links to Vendors that provide Vantage services goto:
http://groups.yahoo.com/group/vantage/links
> Yahoo! Groups Links
>
>
>
>
>
>
>
>



--
No virus found in this outgoing message.
Checked by AVG Anti-Virus.
Version: 7.0.300 / Virus Database: 265.6.11 - Release Date: 1/12/2005