I will give that a try. It doesn't happened often but, I just don't like it when I can't figure it out.
Thank you
Thank you
--- In vantage@yahoogroups.com, brenda mohr <brenda@...> wrote:
>
> We had some odd issues like this and found that some load was not being released. We also re-started the App Server.
>
> Brenda
>
> From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of Cathy
> Sent: Monday, July 22, 2013 12:28 PM
> To: vantage@yahoogroups.com
> Subject: RE: [Vantage] Reschedule a job
>
>
>
> A PO has not been created. The 10 DaysOut does not include Saturday and
> Sunday but, this wouldn't add that much time.
>
> I can't even get the first operation to start today - no labor has been
> charged on the job.
>
> I ignored Constraint materials and tried forward and backward scheduling.
>
> The Subcontract operation is the 3rd operation and has no bearing on the 1st
> operation.
>
> There just seems that we have a few jobs that just done make sense.
>
> From: vantage@yahoogroups.com<mailto:vantage%40yahoogroups.com> [mailto:vantage@yahoogroups.com<mailto:vantage%40yahoogroups.com>] On Behalf Of
> Mike Brown
> Sent: Friday, July 19, 2013 12:45 PM
> To: 'vantage@yahoogroups.com<mailto:%26%2339%3Bvantage%40yahoogroups.com>'
> Subject: RE: [Vantage] Reschedule a job
>
> Well two things could be going on, Is your subcontract days out only days of
> the week or do you include Saturday and Sunday as working days? Another
> thing is if there is a PO date that prohibits the job from starting until
> the PO is received in that will also kick the job out. Did you try forward
> scheduling from Today with Ignore Constrained Materials checked?
>
> Michael Brown
> Master Scheduler / Programmer
> D&S Manufacturing
> 715-284-5376 Ext. 344
>
> From: vantage@yahoogroups.com<mailto:vantage%40yahoogroups.com> <mailto:vantage%40yahoogroups.com>
> [mailto:vantage@yahoogroups.com<mailto:vantage%40yahoogroups.com> <mailto:vantage%40yahoogroups.com> ] On
> Behalf Of cathyattechnologicsys
> Sent: Friday, July 19, 2013 2:32 PM
> To: vantage@yahoogroups.com<mailto:vantage%40yahoogroups.com> <mailto:vantage%40yahoogroups.com>
> Subject: [Vantage] Reschedule a job
>
> We do not have advanced scheduling.
>
> I am just baffled why I cannot get my job to have a due date of 8/5/2013.
>
> The only operation with any significant time is the subcontract operation -
> which has days out of 10.
>
> There are no shortages and I click ignore constraint material. Beside all
> material are on hand.
>
> When I reschedule the job, it gives me a message that "the job is currently
> schedule to finish 8/19.
>
> In Job Scheduling I cannot move the operations to start today.
>
> The resource group has a queue time of 8 - 0 on the resource detail.
>
> Any suggestions? I do not like scheduling.
>
> Thank you
>
> [Non-text portions of this message have been removed]
>
> [Non-text portions of this message have been removed]
>
>
>
> [Non-text portions of this message have been removed]
>