You would probably want to set each operation's crew size to 0.33 for this
particular part routing. I assume you are also using each of these machines
independently at times. If they are always run together as a 3 machine
group it would probably be best to consider the group as a single work
center.
Greg Clauser
Lakin General Corporation
gclauser@... <mailto:gclauser@...>
-----Original Message-----
From: Winter, Patrick [mailto:pjw@...]
Sent: Friday, November 01, 2002 11:04 AM
To: 'vantage@yahoogroups.com'
Subject: RE: [Vantage] Scheduled hours for workcells
Fred
I think I have your solution.
Have you tried Work Cell Machine 1, set to "FINISH-START" scheduling.
Then set up the the second Machine as "FINISH-FINISH" scheduling.
Then setup the third operation/Machine3 as "FINISH-FINISH" scheduling.
This should give you the scheduling accuracy you need.
Note if you work with it you will find "FINISH-FINISH" will work a little
better than "START-START" because you are telling vantage if machine 2 or 3
is a little faster rate than the prior operations that you can't finish
before the prior operation is done, if you know what I mean.
Patrick Winter
sSc Specialty Screw Corporation
Vantage 5.00.338, Progress 9.1a
-----Original Message-----
From: goldbud77 [mailto:fgruber@...]
Sent: Friday, November 01, 2002 9:59 AM
To: vantage@yahoogroups.com
Subject: [Vantage] Scheduled hours for workcells
We have an ongoing problem here with Vantage scheduled hours versus
how jobs are actually ran when we setup workcells. For example, we
have a job that uses (3) separate workcenters(machines) each with its
own operation in the routing. Our workcenters are setup to match one
for one with a specific machine, setup with (1) person and (1)
machine per each of these operations. The problem is that we have the
rate set for these machines equal to the pieces per hour we expect,
let's say 200 per hour. So vantage looks at the hours needed for 200
pieces to be 1 hour for each operation, or a job total of 3 hours.
When in actualy it only takes 1 hour to do all three operations
because only 1 person is running all three machines at the same time.
I am curious at how others have their workcenters and routing setup
for workcell type environments.
Thanks,
Fred
Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must have
already linked your email address to a yahoo id to enable access. )
(1) To access the Files Section of our Yahoo!Group for Report Builder and
Crystal Reports and other 'goodies', please goto:
http://groups.yahoo.com/group/vantage/files/.
<http://groups.yahoo.com/group/vantage/files/.>
(2) To search through old msg's goto:
http://groups.yahoo.com/group/vantage/messages
<http://groups.yahoo.com/group/vantage/messages>
(3) To view links to Vendors that provide Vantage services goto:
http://groups.yahoo.com/group/vantage/links
<http://groups.yahoo.com/group/vantage/links>
Your use of Yahoo! Groups is subject to http://docs.yahoo.com/info/terms/
<http://docs.yahoo.com/info/terms/>
Yahoo! Groups Sponsor
ADVERTISEMENT
<http://rd.yahoo.com/M=237459.2482214.3917349.2146399/D=egroupweb/S=17050071
83:HM/A=1267611/R=0/*http://ad.doubleclick.net/jump/N2524.Yahoo/B1071650;sz=
300x250;ord=1036170273636548?>
<http://us.adserver.yahoo.com/l?M=237459.2482214.3917349.2146399/D=egroupmai
l/S=:HM/A=1267611/rand=529712338>
Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must have
already linked your email address to a yahoo id to enable access. )
(1) To access the Files Section of our Yahoo!Group for Report Builder and
Crystal Reports and other 'goodies', please goto:
http://groups.yahoo.com/group/vantage/files/.
<http://groups.yahoo.com/group/vantage/files/.>
(2) To search through old msg's goto:
http://groups.yahoo.com/group/vantage/messages
<http://groups.yahoo.com/group/vantage/messages>
(3) To view links to Vendors that provide Vantage services goto:
http://groups.yahoo.com/group/vantage/links
<http://groups.yahoo.com/group/vantage/links>
Your use of Yahoo! Groups is subject to the Yahoo! Terms of Service
<http://docs.yahoo.com/info/terms/> .
particular part routing. I assume you are also using each of these machines
independently at times. If they are always run together as a 3 machine
group it would probably be best to consider the group as a single work
center.
Greg Clauser
Lakin General Corporation
gclauser@... <mailto:gclauser@...>
-----Original Message-----
From: Winter, Patrick [mailto:pjw@...]
Sent: Friday, November 01, 2002 11:04 AM
To: 'vantage@yahoogroups.com'
Subject: RE: [Vantage] Scheduled hours for workcells
Fred
I think I have your solution.
Have you tried Work Cell Machine 1, set to "FINISH-START" scheduling.
Then set up the the second Machine as "FINISH-FINISH" scheduling.
Then setup the third operation/Machine3 as "FINISH-FINISH" scheduling.
This should give you the scheduling accuracy you need.
Note if you work with it you will find "FINISH-FINISH" will work a little
better than "START-START" because you are telling vantage if machine 2 or 3
is a little faster rate than the prior operations that you can't finish
before the prior operation is done, if you know what I mean.
Patrick Winter
sSc Specialty Screw Corporation
Vantage 5.00.338, Progress 9.1a
-----Original Message-----
From: goldbud77 [mailto:fgruber@...]
Sent: Friday, November 01, 2002 9:59 AM
To: vantage@yahoogroups.com
Subject: [Vantage] Scheduled hours for workcells
We have an ongoing problem here with Vantage scheduled hours versus
how jobs are actually ran when we setup workcells. For example, we
have a job that uses (3) separate workcenters(machines) each with its
own operation in the routing. Our workcenters are setup to match one
for one with a specific machine, setup with (1) person and (1)
machine per each of these operations. The problem is that we have the
rate set for these machines equal to the pieces per hour we expect,
let's say 200 per hour. So vantage looks at the hours needed for 200
pieces to be 1 hour for each operation, or a job total of 3 hours.
When in actualy it only takes 1 hour to do all three operations
because only 1 person is running all three machines at the same time.
I am curious at how others have their workcenters and routing setup
for workcell type environments.
Thanks,
Fred
Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must have
already linked your email address to a yahoo id to enable access. )
(1) To access the Files Section of our Yahoo!Group for Report Builder and
Crystal Reports and other 'goodies', please goto:
http://groups.yahoo.com/group/vantage/files/.
<http://groups.yahoo.com/group/vantage/files/.>
(2) To search through old msg's goto:
http://groups.yahoo.com/group/vantage/messages
<http://groups.yahoo.com/group/vantage/messages>
(3) To view links to Vendors that provide Vantage services goto:
http://groups.yahoo.com/group/vantage/links
<http://groups.yahoo.com/group/vantage/links>
Your use of Yahoo! Groups is subject to http://docs.yahoo.com/info/terms/
<http://docs.yahoo.com/info/terms/>
Yahoo! Groups Sponsor
ADVERTISEMENT
<http://rd.yahoo.com/M=237459.2482214.3917349.2146399/D=egroupweb/S=17050071
83:HM/A=1267611/R=0/*http://ad.doubleclick.net/jump/N2524.Yahoo/B1071650;sz=
300x250;ord=1036170273636548?>
<http://us.adserver.yahoo.com/l?M=237459.2482214.3917349.2146399/D=egroupmai
l/S=:HM/A=1267611/rand=529712338>
Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must have
already linked your email address to a yahoo id to enable access. )
(1) To access the Files Section of our Yahoo!Group for Report Builder and
Crystal Reports and other 'goodies', please goto:
http://groups.yahoo.com/group/vantage/files/.
<http://groups.yahoo.com/group/vantage/files/.>
(2) To search through old msg's goto:
http://groups.yahoo.com/group/vantage/messages
<http://groups.yahoo.com/group/vantage/messages>
(3) To view links to Vendors that provide Vantage services goto:
http://groups.yahoo.com/group/vantage/links
<http://groups.yahoo.com/group/vantage/links>
Your use of Yahoo! Groups is subject to the Yahoo! Terms of Service
<http://docs.yahoo.com/info/terms/> .