Whilst testing during our 9.05 implementation we found that without the
APS module the 'constrained' flag within the part master was ignored
when scheduling jobs.
Chris HenzelEpicor 9 Project ManagerTel: +44 (0)1582 436150Mob: 07836 314164
This message contains confidential information and is intended only for the intended recipients. If you are not an intended recipient you should not disseminate, distribute or copy this email. Please notify the sender if you have received this email by mistake and delete it from your system.Email transmission cannot be guaranteed to be secure or error-free as information could be intercepted, corrupted, lost, destroyed, arrive late or incomplete, or contain viruses. The sender does not accept liability for any errors or omissions in the contents of this message, which arise as a result of email transmission. Registered Office: Hayward Tyler Ltd, 1 Kimpton Road, Luton, LU1 3LD, England. Tel: +44 (0)1582 731144. Company No. 3450138.
-----Original Message-----
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of Ken Williams
Sent: 24 July 2011 16:27
To: vantage@yahoogroups.com
Subject: RE: [Vantage] Scheduling system & the APS module question
By default, without APS, the system WILL take into material due dates
into account and won't schedule a job ahead of material. It's easy to
override ("Override Material Constraints") when scheduling, but
otherwise it definitely takes material due dates into account.
Ken
________________________________
From: vantage@yahoogroups.com [vantage@yahoogroups.com] On Behalf Of
jim_chance [jim_chance@...]
Sent: Sunday, July 24, 2011 7:55 AM
To: vantage@yahoogroups.com
Subject: [Vantage] Scheduling system & the APS module question
I have heard the following statement from someone about there use of the
Epicor Vantage 8 or 9 scheduling system.
Can someone confirm this is a true statement.
Thanks.
"
We have purchased the APS module so that the scheduling will take the
material due date into account. Without APS the material is assumed to
be available."
[Non-text portions of this message have been removed]
------------------------------------
Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must
have already linked your email address to a yahoo id to enable access. )
(1) To access the Files Section of our Yahoo!Group for Report Builder
and Crystal Reports and other 'goodies', please goto:
http://groups.yahoo.com/group/vantage/files/.
(2) To search through old msg's goto:
http://groups.yahoo.com/group/vantage/messages
(3) To view links to Vendors that provide Vantage services goto:
http://groups.yahoo.com/group/vantage/linksYahoo! Groups Links
APS module the 'constrained' flag within the part master was ignored
when scheduling jobs.
Chris HenzelEpicor 9 Project ManagerTel: +44 (0)1582 436150Mob: 07836 314164
This message contains confidential information and is intended only for the intended recipients. If you are not an intended recipient you should not disseminate, distribute or copy this email. Please notify the sender if you have received this email by mistake and delete it from your system.Email transmission cannot be guaranteed to be secure or error-free as information could be intercepted, corrupted, lost, destroyed, arrive late or incomplete, or contain viruses. The sender does not accept liability for any errors or omissions in the contents of this message, which arise as a result of email transmission. Registered Office: Hayward Tyler Ltd, 1 Kimpton Road, Luton, LU1 3LD, England. Tel: +44 (0)1582 731144. Company No. 3450138.
-----Original Message-----
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of Ken Williams
Sent: 24 July 2011 16:27
To: vantage@yahoogroups.com
Subject: RE: [Vantage] Scheduling system & the APS module question
By default, without APS, the system WILL take into material due dates
into account and won't schedule a job ahead of material. It's easy to
override ("Override Material Constraints") when scheduling, but
otherwise it definitely takes material due dates into account.
Ken
________________________________
From: vantage@yahoogroups.com [vantage@yahoogroups.com] On Behalf Of
jim_chance [jim_chance@...]
Sent: Sunday, July 24, 2011 7:55 AM
To: vantage@yahoogroups.com
Subject: [Vantage] Scheduling system & the APS module question
I have heard the following statement from someone about there use of the
Epicor Vantage 8 or 9 scheduling system.
Can someone confirm this is a true statement.
Thanks.
"
We have purchased the APS module so that the scheduling will take the
material due date into account. Without APS the material is assumed to
be available."
[Non-text portions of this message have been removed]
------------------------------------
Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must
have already linked your email address to a yahoo id to enable access. )
(1) To access the Files Section of our Yahoo!Group for Report Builder
and Crystal Reports and other 'goodies', please goto:
http://groups.yahoo.com/group/vantage/files/.
(2) To search through old msg's goto:
http://groups.yahoo.com/group/vantage/messages
(3) To view links to Vendors that provide Vantage services goto:
http://groups.yahoo.com/group/vantage/linksYahoo! Groups Links