Hi,
We run MRP once a week and some of the unfirm jobs it generates have an incorrect start and due date. Ex: The Required by is 5/12/17, the due is 4/24/17 and the start is 4/17/17. I’m not sure why the due date is 2 weeks early. We schedule backward, no finite schedules in any resources, no queue times… I don’t know what else to check. Any ideas?
Thanks
Melissa