Anyone have any suggestions or similar issues? Perhaps you could
just provide some input on how you handle Jobs with one Subcontract
Operation.
just provide some input on how you handle Jobs with one Subcontract
Operation.
--- In vantage@yahoogroups.com, "Brian" <brian.chandler@...> wrote:
>
> We are trying to figure out an issue we have with MRP. Let assume
we
> have a sales order for 1000 of a part with a lead time of 30
days.
> The 30 day lead time was set by using a part class with the
Receive
> Field on the class set to 30. It is setup as Make to Stock with a
Min
> Lot size of 1000. In addition the Method has the Days Out set to
20
> days.
>
> We create a job to support this order with the following dates
> Req By: 05/28/2008
> Start: 03/19/2008
> Due: 04/16/2008
>
> The problem is that the suggestion gets created correctly the
first
> time we run MRP. The next time we run MRP w/Regenerative option
> selected it will create a suggestion to change the Due Date to
> 5/28/2008.
>