PO Requisitions for Jobs

In E10, a PO Requisition can be done for a Job, but the requisition screen doesn’t let you select which part from the job you’re ordering. Then we get an error message when we try to create the PO saying the job is already engineered and another part can’t be added. Any ideas?

Hi Tim,

Have you tried checking purchase direct on the job material?

Nancy

You can’t select pre-detailed materials via a Purchase Order Requisition in the out of the box version of Epicor, however I’ll qualify this by saying Epicor ARM (add-on) allows you to do so apparently.
By detailing the material requirements into the job and marking the job as Engineered/Released is by default approving the content and making the materials available for Purchasing to run a Purchase Order Suggestions Report. Purchase Orders are then created from that.
Materials requested via POR are added to ASM0 only, you can’t request a material for a Sub-Assy as far as I know.